Blog header

Blog header

Thursday, January 31, 2013

#101 - Tenova Projects - The TATA Steel Richardsbay Furnace


In May 2006, global steel producer Tata awarded a contract to Tenova Pyromet for the Tata KZN Project. The plant is located in Richardsbay Kwa Zulu Natal South Africa

The project was for design, supply, installation and commissioning of 2 x 36-MVA closed submerged arc furnaces. A submerged arc furnace is a type of electric arc furnace (EAF) in which the electrodes are buried deep inside the furnace burden or load. In a normal EAF, the electrodes hover slightly above the load to induce the arc.

Scope: A complete furnace technology package for 2x submerged arc furnaces including the plant control system, with electrical and mechanical equipment. The scope also included the entire gas-cleaning scrubber system for the furnace off gas, as well as the tap hole fume extraction system.

Commissioning of both furnaces was successful as the first furnace was commissioned in April 2008, and the second furnace in May 2008.

The smelter incorporates the following technology:
· Pyromet submerged arc closed furnace technology
· Pyromet patented electrode columns
· Complete plant automation system designed by Pyromet
· Pyromet designed furnace off-gas scrubbers, two per furnace



Challenges Overcome

One of the major challenges was the correct process design of the furnaces with the design requiring that the furnaces treat chrome ore briquettes. The ore used to prepare the briquettes would be sourced from India.

The logistical challenge of doing a project in Richards Bay was that the equipment had to be designed to withstand the rigorous demands of coastal conditions. Local suppliers had to be sourced for the manufacturing and installation of equipment to save on logistical costs.

The quality of the off gas cleaning system complies with a very strict environmental requirement due to the location of the plant in close proximity to a residential area as well as the strict environmental bylaws governing the area which is an ecological preserved area.

The furnace building structure was supplied from India and the integration of the equipment to the furnace building structure had to be designed and fitted accordingly.

The site team had to endure coastal conditions where wind, rain and sandy terrain complicated planning and execution of certain tasks.

Project Statistics
Concrete: 12 000 rn'
Steel structures: 4800 tons
Construction man-hours: > 1 million
Pyromet project team: 9 persons
Project site team: 25 persons
Furnace produces: 133 000 tons per annum
Furnace capacity: 142 857 tons per annum
Furnace type: Closed Furnace
Project duration: 24 Months - April 2006 to April 2008

Tenova PYROMET
Tenova Pyromet (Pty) Ltd
10 Sherborne Road
Parktown, Johannesburg
PO Box 61582, Marshalltown
2107 South Africa
Phone +27 11 480 2000
Fax +27 11 482 1942
E-mail: pyromet at za dot tenovagroup dot com


NOVA Analytical Systems
1-800-295-3771
sales at nova-gas dot com
websales at nova-gas dot com

1 comment:

Anonymous said...


As I think of the Mayville Iron Works, and its two blast furnaces and coke plant which were demolished not
long after that iron works closed in 1928, I'm grateful for this amazing site which still stands.
Here are the Carrie Furnaces outside of Pittsburgh, with two 200 feet high blast furnaces, hot blast stoves
and beautiful smokestack.

air conditionin
air conditioner
ac air conditioning
furnace
hvac

Post a Comment